CREC4-built sewage plant in Ulaanbaatar reaches new milestone
With the help of a Chinese State-owned enterprise, Mongolia's No 1 project concerning people's livelihoods-a new central sewage treatment plant in the capital that will benefit 45 percent of the nation's residents-is on its way to a smooth completion and acceptance by August next year.
Construction of the plant in Ulaanbaatar, capital of Mongolia, being built by the First Engineering Co Ltd of China Railway No 4 Engineering Group Co Ltd (CREC4), hit another milestone on March 31 with the successful concrete pouring into the inner walls of three reaction tanks.
This marked the simultaneous completion of three planned construction nodes in building the plant, dubbed the No 1 public wellbeing project of Ulaanbaatar, since the resumption of construction work from the COVID-19 disruptions.