China-built Jakarta-Bandung HSR sees landmark progress

By MA CHENGUANG and ZHUANG QIANGE | China Daily | Updated: 2022-11-30 00:00

With a 900-metric-ton beam being safely positioned along the No 24 Bridge on the Jakarta-Bandung High-Speed Railway on Oct 16, all the box beams on the line had been successfully installed, meaning that track-laying work can begin.

At present, all 13 tunnels for the HSR in Indonesia are fully connected, laying a solid foundation for its planned operation by June 2023, said Han Xinliang, a publicity official from China Railway No 4 Engineering Group Co Ltd.

The $8-billion Jakarta-Bandung HSR, as Chinese HSR's first systemic footprint overseas and the first HSR in Indonesia as well as in Southeast Asia, is a signature link of the Belt and Road Initiative.

Report cites rights progress in Tibet

Most Viewed

Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US