Nation's 1st modular 500-kV substation online

By LI JIAYING | China Daily | Updated: 2025-05-28 00:00
Share
Share - WeChat

China's first fully modular 500-kilovolt ultrahigh voltage substation recently began operations in Fucun township, Jinhua, Zhejiang province.

The Pancun village substation was completed in just 14 months by employing an innovative construction method that combines prefabricated assembly with intelligent systems — a process described as akin to "building with blocks", said its major constructor State Grid Zhejiang Electric Power.

Over 80 percent of the substation's modular components, including the steel-structured control room and firewalls, were prefabricated off-site and assembled directly on location. The approach has reduced the construction timeline by four months compared to traditional methods, cut high-above-ground work risks by 50 percent and minimized dust pollution, reinforcing a commitment to environmental sustainability, according to the builder.

Report cites rights progress in Tibet

Most Viewed

Top
BACK TO THE TOP
English
Copyright 1994 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US